top of page

UPDATES: Lower Wicomico River Maintenance Dredging Project

While DIPP is a sponsor of the project, we are doing our best to use our network to stay up-to-date on the project and communicate that information. We will keep this page up-to-date, with the latest news on the Maintenance Dredging Projects and the impacts you will see.

Update 5/26/2023

The next phase of the Beneficial Use project at the Deal Island WMA is to install conduit for the dredge pipeline to pass under Rt. 363. This construction will begin after June 15th. 

 

What can you expect?

  • Heavy equipment and construction crews on site

  • Potential brief delays in traffic when construction vehicles are moving onto the road

 

The contractor will use the “jack and bore” method to install a 48” diameter steel casing below Deal Island Road/ MD Rt 363 just east of the Messix Road intersection. Once the casing pipe is installed, a 30” diameter reinforced concrete carrier pipe will be installed within the casing pipe. To install the casing and carrier pipes, the contractor will have to excavate a sizeable boring pit south of the roadway, and a smaller receiving pit north of the roadway, to accommodate the machinery and materials needed to install the conduit pipes.  After construction activities have been completed, the casing pipe is to be sealed, the marshes are to be restored to elevation, and eventually planted with appropriate marsh plants during the next growing season.   

 

During active dredging operations, the dredging contractor will install a section of the plastic dredge pipeline coming from Dames Quarter Creek through the carrier pipe under the roadway to carry the materials farther south to the deposition areas.  After the dredging project is completed, the plastic dredge pipeline will be removed. 

 

See “Culvert Placement” project plans for more details, or contact Brian Wilkins, Engineer, Wicomico County Department of Public Works at (410) 548-4927.

Update 5/16/2023

Effective Friday, May 19, 2023, the section of Riley Roberts Road (extended) where it enters the Deal Island WMA will be reopened to vehicle traffic without weekday restrictions. Visitors to the WMA should exercise caution to avoid the dredging pipe staged along the road margin and in the borrow ditch along Riley Roberts Road extended.  Construction activities in the area of our South parking lot / Broad Creek boat ramp will be winding down during the week of May 15th until anticipated to resume in early to mid-September. 

Updated 5/1/2023

Riley Roberts Road has been closed for much of April and is scheduled to reopen in the next couple of weeks. The exact date is unknown. The contractor needs to finish unloading and placing 500 foot sections of pipe along the road.

 

The straw bale containment and ditch plug construction wrapped up at the end of April. The straw bale containment and ditch plugs will remain in place through the summer. The contractor will assess the containment in late August and complete any repairs needed prior to sediment placement which will begin in October 2023.

 

Planting of the site will occur in either 2024 or 2025 depending on the firmness of the dredge materials.

 

For the most current information regarding project progress and facilities restrictions through the course of the project, please visit the Deal Island WMA webpage at: https://dnr.maryland.gov/wildlife/Pages/publiclands/eastern/dealisland.aspx.

 

For more specific questions, please contact the Wellington WMA office at (410) 651-2065, or John Moulis, Eastern Regional Manager, at (410) 827-8612, x105.

culvert plans.jpg
USACE.png
bottom of page